Process Engineering Waterproofing For New Construction

SENO, FLOOR ROOF, FLOOR CLEANING
I / - Cleaning the surface to be waterproof.
- Use a hammer and wood chisel coffa balance the lake also stick on the concrete surface.
- Use clean water and clean the concrete surface.
- To dry concrete surface before handling the waterproofing.
II / - To handle waterproof concrete surface.
Step 1: Penetration of concrete surface.
- Phase 1 liter Intoc 04 + 18 liters of water + 3 kg cement, stir and pour onto the surface to permeable concrete (osmosis will generate saturated humidity and stagnant pools of water but not to proceed with Step 2)
Step 2: Scan the surface.
- Phase 1 liter 4 liters of water Intoc 04 + 4 liters of water + 3 to 4 Kg cement, stir and then scan the surface (avoid omitted).
III / - Officials of mortar to create the slope: the slope reaches a minimum of 1%.
- Step 2 When the surface was completely dry, then proceed created steep rolling
IV / - To handle waterproof surface slope lakes.
Step 1: Penetration of mortar to create the slope surface.
- Phase 1 liter Intoc 04 +
18 liters of water + 3 kg cement, stir and pour onto the surface to osmosis (osmosis will generate saturated humidity and stagnant pools of water but not to proceed with Step 2)
Step 2: Scan the surface.
- Phase 1 liter Intoc 04 + 5
liters of water + 3 to 4 Kg cement, stir and pour each region are scanned onto the surface.
Note: - If the surface waterproofing spray drying must be maintained
- Once Step 2 has been completely dry then go back on it or brick

LAKE WATER
I / - Cleaning the surface to be waterproof.
- Use a hammer and wood chisel coffa balance the lake also stick on the concrete surface.
- Use clean water and clean the concrete surface.
- To dry concrete surface before handling the waterproofing.
II / - To handle waterproof concrete surface.
Step 1: Penetration of concrete surface.
- Phase 1 liter Intoc 04 +
10 liters of water + 3 kg cement, stir to scan the surface permeability of concrete (both moisturizing and osmosis water saturation to proceed with Step 2)
Step 2: Scan the surface.
- Phase 1 liter 4 liters of water Intoc 04 +
4 liters of water + 3 to 4 Kg cement, stir and then scan all the surface.
III / - Fill up and the lake bed.
- Step 2 When the surface was completely dry, then proceed fill the tank.
IV / - To handle waterproof paint on stucco surfaces.
Step 1: Penetration of concrete surface.
- Phase 1 liter Intoc 04 +
10 liters of water + 3 kg cement, stir and then scan the surface to the mortar bowl osmosis (osmosis will generate humidity and water saturation to proceed with Step 2)
Step 2: Scan the surface.
- Phase 1 liter 4 liters of water Intoc 05 +
4 liters of water + 4 to 5 Kg cement, stir and then scan the surface.
Note: - If the surface waterproofing spray drying must be maintained.
- Step 2 When completely dry, the new movement, or paved over.

VERTICAL WALL, WALL SONG
I / - Cleaning the surface to be waterproof.
- Scrape steel trowel the mortar they intend to paint on the walls.
- Use clean water wall surface.
II / - To handle waterproof.
Step 1: Scan permeable layer.
- Phase 1 liter Intoc 04 +
18 liters of water + 3 kg cement, stir to scan the surface of permeable surface paint stucco wall (osmosis will generate humidity and water saturation to proceed with Step 2)
Step 2: Scan the surface layer.
- Phase 1 liter Intoc 04 +
5 liters of water + 3 kg cement, stir and then scan all the surface (avoid omitted).
Step 3: Scan the surface.
- Phase 1 liter Intoc 05 +
5 liters of water + 3 kg cement, stir and then scan all the surface (avoid omitted).
Note: - If the surface waterproofing spray drying must be maintained.
- After the waterproofing layer is completely dry paint proceed, whitewashing.